By Maureen Odunga
THE construction of the much awaited first flyover in the country at Tazara by the junction of Nelson Mandela Expressway and Nyerere Road in Dar es Salaam is on course, having reached 45.3 per cent.
Works, Transport and Communications Minister, Prof Makame Mbarawa, revealed this yesterday after inspecting the construction site for the second time, this year. "I am pleased to see that the project is progressing well and it is in line to the set target of 45.4 per cent as indicated in the timeframe," said Prof Mbarawa.
He observed that the progress was an important milestone in the timely completion of the project by end of October 2018. "When I visited the site in February, this year, the construction work was at 25 per cent and up to this juncture another 20 per cent has also been completed.